Instant development feasibility

1260 Journeys End Cir

Newmarket, Ontario. What could be built here, how big, how long it takes to approve, and what the land could be worth to a builder.

Illustrative estimate from public records and your inputs. Not an appraisal, a zoning opinion, or a guarantee of approvals. LSG Realty Inc., Brokerage.

The lot

Lot area
9,903 m²Property report: lot area from the public parcel data
Frontage and depth
106.5 m × 118.3 mProperty report: estimated from the lot lines (not a survey)

One plausible scenario

Scenario 1

Mid-rise, about 226–379 units (needs rezoning)

A mid-rise apartment building, if the City approves a rezoning.

  • Gross floor area24,758–34,661 m² (266,487–373,082 sq ft)
  • Units226–379 units
  • Approval pathRezoning (Zoning By-law Amendment) and site plan; not permitted today
  • Timeline12–24 months approvals + 24–36 months construction

Not permitted under today's zoning. Shown to illustrate what an approval could allow; approval is not assured.

How we estimated it
Station area
Highway 404 (protected MTSA), target 160Property report: Major Transit Station Areas
Official Plan
Urban AreaProperty report: Official Plan designation
Density
FSI 2.5–3.5 × 9,903 m² = 24,758 m²–34,661 m²Mid-rise density FSI 2.5 to 3.5 (typical, needs confirmation)
Units
82% sellable ÷ 75–90 m² = 226–379Average unit 75 to 90 m² (typical, needs confirmation)
Timeline
approvals 12–24 months, construction 24–36 monthsApproval and construction months (typical, needs confirmation)

Key risks

  • Not permitted today: a mid-rise building needs a rezoning (and site plan approval); the outcome is not assured.
  • The local Official Plan may also need an amendment to reach this height and density.
  • Protected station areas can require affordable units (inclusionary zoning).
  • Height and density depend on angular planes, shadow, parking and the City's urban design guidelines.
  • Servicing: Limited: reserved for priority projects. Larger projects may wait for water and sewer allocation.
Rough budget and residual land value

Enter your own figure. We could not verify the Altus Group 2026 Canadian Cost Guide ranges (free download at altusgroup.com/featured-insights/canadian-cost-guide); use its range for this building type in your market, or a builder's quote.

Your own estimate of what the finished space sells (or is worth) per sq ft. This public tool does not use MLS® sales data.

Design, permits, consultants, legal, insurance and marketing: commonly 15–25% of hard cost (typical, needs confirmation).

Every new unit after the first (credit for the existing house) is charged. Rates: York Region development charges, By-law 2026-20, effective May 21, 2026, full water and wastewater (single/semi $84,718; multiple $72,392; apartment 700 sq ft or more $58,721) · Education development charge in York Region (public and Catholic boards), $8,934 per dwelling (combined guide effective July 1, 2026) The local municipality's own development charge is not in our table yet: add it to the per-unit figure.

Construction loan rate (typical, needs confirmation).

On average about half the cost is drawn over the build (typical).

Builder's margin on revenue: commonly 12–20% (typical, needs confirmation).

Share of gross floor area that is sellable or rentable (walls, stairs and halls excluded).

Enter a hard cost and a sale value per sq ft to see the residual land value.

Get a free feasibility review from an LSG land specialist

LSG Realty's parent company has 20 years of land and development work in the GTA. A land specialist will check the zoning, the numbers and the approval path with you, at no cost.

We send the specialist your contact details, this address, and the scenario summary above (not the budget figures you typed). See our privacy policy.

Illustrative estimate from public records and your inputs. Not an appraisal, a zoning opinion, or a guarantee of approvals. LSG Realty Inc., Brokerage.

See the full property report for this address · Builders and investors looking for sites like this · How this works